Blanchardstown Data Centre
Print pageDevelopment location:
Unit 5A Blanchardstown Corporate Park, Ballycoolin, dublin_15
Description:
New ESB substation, transformer compound with palisade fence and LV substation. Alterations to existing building façade to accommodate new plant. New mezzanine floor in existing warehouse and conversion of warehouse area to data centre. New 4.9m high screen wall to existing external plant. Part fit out of existing office space and all associated site works.
Notice type:
Commencement Notice With Compliance Documentation
Notice number:
CN0009294FL
Commencement date:
Friday, 31 July, 2015
Submission date:
Friday, 17 July, 2015
Owner:
Owner name:
Michael Hannon
Builder:
Builder name:
James Wilman
Designer:
Designer name:
Richard McCrae
Certifier:
Assigned Certifier Name:
Richard McCrae
Certificate of Compliance on Completion:
Completion Certificate No.:
CC00000013870FL
Total Units on this CC:
1