IT Carlow Sports Campus Development - Phase 2 - Civil Works
Print pageDevelopment location:
5B Maple Court, Carlow, carlow, R93 C9K3
Description:
Construction of new ESB Sub-station/Switchroom, construction of new front boundary wall along western boundary and all associated ancillary services and civil works.
Notice type:
Commencement Notice With Compliance Documentation
Notice number:
CN0045910CW
Commencement date:
Wednesday, 28 November, 2018
Submission date:
Wednesday, 31 October, 2018
Owner:
Owner name:
Keith Williams
Owner address:
Estates Department
Institute of Technology Carlow
Kilkenny Road, Carlow, carlow
Builder:
Builder name:
Paul Patterson
Builder address
49
Ballynahinch Road, Saintfield, down, BT24 7ND
Designer:
Designer name:
Brendan Heaney
Designer address
Tobin Consulting Engineers
Fairgreen House
Fairgreen Road, Galway, galway
Certifier:
Assigned Certifier Name:
Brendan Heaney
Assigned Certifier address
Tobin Consulting Engineers
Fairgreen House
Fairgreen Road, Galway, galway
Certificate of Compliance on Completion:
Completion Certificate No.:
CC00000022832CW
Total Units on this CC:
1
Address:
Mprtarstown Upper
Carlow
IT Carlow Sports Campus
Mortarstown Upper