Welcome to the Building Control Management System (BCMS)

Notice Name:

Ashewood Walk - Houses 105-128

Print page
Development location: 
Summerhill Lane, , Portlaoise, Laois,
Description: 
Construction of Houses 105-128 (Site Plots 47-70 as Per Planning Permission) at Ashewood Walk, Summerhill, Portlaoise, Co. Laois.
Notice type: 
Commencement Notice With Compliance Documentation
Notice number: 
CN0108717LS
Local authority: 
Laois County Council
Commencement date: 
Wednesday, 3 January, 2024
Plannning permission number: 
23164
Submission date: 
Tuesday, 12 December, 2023

Owner:

Owner name: 
Brian Dempsey

Builder:

Builder name: 
Brian Dempsey

Builder address

Frank Fahey Centre, Naas Road, Dublin 12, Dublin,

Designer:

Designer name: 
Paul Bergin

Designer address

Kilgallen & Partners Consulting Engineers, Portlaoise, Laois, R32 P668

Certifier:

Assigned Certifier Name: 
Paul Bergin

Assigned Certifier address

Kilgallen & Partners Consulting Engineers, Portlaoise, Laois, R32 P668

Certificate of Compliance on Completion:

Completion Certificate No.: 
CC00000052486LS
Total Units on this CC: 
6
Address: 
Summerhill, Portlaoise, Laois Nos. 123 -128 Ashewood Walk